500 Vehicles in and out every day! A Return Visit to EOUNICE Intelligent Parking System of XingTang Hospital accomplished in 2021
【Xintang Hospital 】is located in the old town of Xintang, surrounded by old residential areas and villages with narrow roads. Xintang Hospital has a large daily flow of people and vehicles, and there are often road blockages. Before building an automated parking system, parking space was scarce, and it was too difficult to come to see a doctor. Sometimes people would be charged indiscriminately, which caused many problems for urban management.
Roads are congested
Parking is difficult on the perimeter
Shortage of parking spaces in the old parking lot
With strong capabilities of technical research and development, highly coordinated production, and manufacturing strength, EOUNICE designed a 5-level lifting and traversing parking system for XingTang Hospital, which was divided into three parking areas and provided 150 parking spaces, helping to solve the lack of parking spaces and difficult parking around Xintang Hospital, and effectively improving road traffic congestion. The sufficient parking spaces greatly enhanced the parking experience and added more convenience.
EOUNICE INTELLIGENT PARKING SYSTEM LIVE SHOOTING
HIGHLIGHT OF EOUNICE INTELLIGENT PARKING SYSTEM
5-layer Puzzle Parking System
Greater allowable car size
The project adopted a 5-level lifting and puzzle parking system design, covering an area of 1135 square meters, with a total height of 10 meters. The project was equipped with a complete intelligent parking guidance system, which has increased to 150 parking since there were only 50 before. Increase land use rate to 200%. The size of the parking space is 5300mm*2200mm*1850mm, suitable for more models, which can effectively solve the phenomenon of insufficient parking spaces resulting in road congestion outside, delaying medical treatment, and “parking for half an hour, seeing a doctor for 10 minutes”. The design of sufficient and considerate parking spaces also greatly improves the parking experience of car owners.
Living Shooting
To facilitate the public store and pick up the car, the project is divided into three sections, and the entrances and exits are separated. It made full use of the area as much as possible, accelerated the entry and exit of traffic flow and the allocation of parking spaces, and reduced the waiting time. At the same time, 15 ground parking spaces were also retained for oversized vehicles. The exterior of the equipment is decorated with guardrails to protect vehicles from wind, rain, and dust.
Project Operation
Since the completion of the project at the end of October 2021, it has been in operation for nearly 3 years, with 500 vehicles entering and leaving each day. After the stereo garage was completed and put into use, it helped solve the parking demand around Xintang Hospital, reducing the road congestion caused by the shortage of parking spaces, delayed medical treatment, traffic accidents, inconvenient medical parking, and crowded fire and ambulance channels. It provides more smooth and convenient parking facilities, saves land resources, and greatly improves the parking, travel, and medical experience of the owner.